Hi all
In the current project we are currently on SRM 7.02 in ECS. We are looking to perform Mass update of POs, however we are aware that this functionality is not standard in SRM.
Using Transaction MASS, for goods we can close old POs in mass by having the checkbox "Delivery Complete" in SAP ECC checked. This is turn is replicated to SRM by having the "No Further Confirmation" synchonised to "Yes".
However, for Services / Limit POs, the "Delivery Complete" checkbox in SAP ECC seems to be missing. Does anyone know how to enable this functionality (Delivery Complete) in ECC or know how to perform Mass PO Closure/Update for Service/Limit POs?
Any other ideas or solutions would be greatly appreciated.
Thanks a lot