Hi Experts,
SRM 7 EHP 1
ECC 6 EHP 3
Classic scenario
We have Funds Management and Investment Management modules performing budget check during PR creation in ECC. There are no customizations and the standard configurations have been used for budget allocation etc.
Queries -
1. While trying to create a SC in SRM will the same type of budget checks (as per ECC) be applicable on the account assignment objects used in the SC?
2. Is there any restricition on the account assignment objects on which the budget check functionality works in SRM?
3. Does the commitment get posted in ECC during creation of SC / approval of SC / on creation of PO? Is this dependent on the configuration set for commitment posting in ECC?
Thanks a lot.
Regards,
Amish